Perry Community Meeting at Tap That Growlers in La Grande 7pm-9pm
Wrapped up all operations on the Site
Walked all equipment off the Site
Wrapped up ALL DRILLING OF CORE SAMPLES ON SITE
Continued drilling on X-10 (weather delays)
Continued drilling on X-10
Drilling on X-10... ended the day at 187 feet depth (Exceptional Ballast Rock Collected/Documented)
Drilling on X-10 (Exceptional Ballast Rock Collected/Documented)
Completed X-8 Boring, Moved Drill from X-8 to final Boring Location X-10... drilled to 23'
X-8 Boring Continued (Exceptional Ballast Rock Collected/Documented)
X-8 Boring Continued (Exceptional Ballast Rock Collected/Documented)
X-8 Boring Continued (Exceptional Ballast Rock Collected/Documented)
X-8 Started Boring - 400' depth planned
Completed 400' boring and started move to X-8 in center of hillside
Currently drilling on X-7
Continued drilling X-7 and punched through to 297' by end of day... mostly high quality basalt. (Drilling to 400')
Started drilling X-7 and collecting core samples, just below 10' depth hit excellent Basalt and ended the day at 100' depth with continuous basalt
X-13 Boring was completed with Excellent Basalt Core Samples Collected, End of Day moved to X-7 up on the Mountain (400' depth)
X-12 Boring was completed and core samples collected, moved a short distance east to X-13 and set up
Set up the Drill on X-12 and began drilling a 50' depth for core samples
Planning to Complete Boring X-11 at 200 Feet of Depth before Moving to Boring Site X-12
On site X-11 drilling ended the day at 158 feet depth of core samples on a 200' boring.
Drilling on Site X-11 ended the day at 104' depth of core samples on a 200' boring.
Moved Drill and Equipment from X-4 to X-11 and began Drilling at 2pm, ended the day at approximately 54'
Completed Boring on X-4 site to 200' Depth with Core Samples